Historical Timeline

 1307 North Main Street P.O. Box 416 Mount Airy, Maryland  21771  

301-829-0325


History of the St. James' Building Effort

THE SPIRIT IS BUILDING TIME LINE   √ = step completed.  


March 1999

  LAND PURCHASE

St. James' Parish Family completed  the purchase of 12 acres on North Main Street, about 0.8 miles north of the current location.

 

June 2000

  TOWN ANNEXATION

The town of Mt. Airy and Carroll County approved the annexation of the new land site into the town.  This was done in order for St. James' to have access to public utilities.

January 2001

LAND LOAN PAID OFF

November 2000 - St. James' Vestry made the decision to pay off  the land loan. 

 January 2001 - The loan was paid off.

May 2001

EPISCOPAL CHURCH BUILDING FUND PROCESS IMPLEMENTED

The Land Planning Committee (LPC) recommended to the Vestry that this process be used by lay committees to do many of the tasks that will help to identify the parish's building needs.  The Vestry approved this concept.

August-November 2002

SUMMARY REPORT

August 20, 2002 Submitted to Rev. Portia & the Vestry, which included building needs of St. James' ministries, proposed building options and a building timeframe.  Rev. Portia & Vestry provided parish family with opportunities to review LPC report and share feedback through sermons, adult forums, newsletters, parish dinner and other times for fellowship.

 September 29, 2002 - LPC Report was presented to parish family at St. James' ''Pot Luck'' dinner. 

INTERVIEW & SELECT ARCHITECT and/or CONTRACTOR  who will prepare a Master land concept plan, incorporate our bldg. ministries' needs into preliminary drawings & floor plans, and furnish preliminary construction estimates.  

September 26, 2002 - Interviews completed.  

October 7, 2002 - LPC Meeting- Report by LPC Building subcommittee on interviews with architect and/or contractors.  Bids opened and discussed.

November 3, 2002 - The architect firm of Noelker and Hull Associates (Chambersburg, PA) was selected & placed under contract to provide master land/building planning services

 November 2002 - October 2003

MASTER PLAN  - This plan includes:  land concept plan, preliminary drawings, floor plans & construction estimates. 

Spring 2003 - Master plan completed to support future planning, as well as an information base for the Capital Campaign.

The master plan was composed of two phases: phase one consisting of a parish hall or great hall (to be used initially as the sanctuary), classrooms for Sunday School and Nursery School, a kitchen, restrooms, and other needed infrastructure (ie. elevator, mechanical space, parking, etc.) Phase two, to be developed sometime in the future, would add a permanent sanctuary and additional classroom and outreach space.

 

INTERVIEW & SELECT A CAPITAL CAMPAIGN CONSULTANT

This consultant was to conduct a feasibility study to determine if a Capital Campaign would raise sufficient funds to support a new building project. Additionally, the consultants would be an ongoing source of support and help throughout our Capital Campaign, if we decided to continue.

June 11, 2003 - Selected Hollimann Associates to be the Capital Campaign consultant for the feasibility study.  A Capital Campaign committee was established to work with the consultant and lead the effort.

 

CONDUCT FEASIBILITY STUDY

 September 16, 2003 - Holliman Associates submitted the completed feasibility study to the Capital Campaign committee and the Vestry

October 12, 2003 - The results of the feasibility study were presented to the congregation by the Capital Campaign committee.  Based on the results of the study and parish feedback, it was decided that the master plan should be modified to reflect the likely outcome of the fundraising campaign.  Accordingly, a building committee was established (replacing the land planning committee) to carry out the master plan revisions as well as future "new building" tasks as appropriate. The Capital Campaign was scheduled to begin once the new plan was in place.

November 2003 - Fall 2004

REVISED MASTER PLAN & CAPITAL CAMPAIGN

February 12, 2004 - A parish meeting was held by the building committee with Noelker and Hull present to discuss the congregation's priorities and preferences for the first phase of the new building, consistent with the outcome of the Capital Campaign feasibility study.

April 30, 2004 - The revised master plan was completed by Noelker and Hull and accepted by St. James'.

Spring 2004 - The Capital Campaign brochure, based on the feasibility study and the revised master plan, was completed to support initiation of the the campaign

September 25, 2004 - The formal Capital Campaign was kicked off with a congregation wide celebration at the Linganore Winery in Mt. Airy.

Fall 2004 - The Capital Campaign was completed successfully.  St. James' committed to move forward with the new building project.

 

Winter 2004 - 2005

OBTAINED SPECIAL ZONING EXEMPTION - This zoning decision was needed to allow a church to be built within a residential zoned area.  Van Mar Associates was under contract to provide zoning application support and to prepare site planning documents for Town and Carroll County approval.

November 29, 2004 - The Town of Mt. Airy held its Planning Commission Public Hearing to consider the special exemption zoning application filed by St. James' in October 2004.  

January 25, 2005 - The Town of Mt. Airy Board of Appeals held a public hearing and approved the special exemption zoning for the new church building.

 

ESTABLISHED BUILDING COMMITTEE SUBCOMMITTEES to begin the process of defining in detail the design requirements for the new building and to oversee its development.

February  2005 - seven subcommittees were established - Design Oversight, Construction Oversight, Nursery School/Sunday School, Worship, Kitchen/Hospitality, Office/Administration, Environmental Factors.

 

HIRED ARCHITECT

March 15, 2005 - St. James' signed a contract with Noelker and Hull Associates to provide full architectural and engineering services for the new church building.

Summer 2005

 SUBMITTED SITE PLAN & ADEQUATE PUBLIC FACILITIES ORDINANCE (APFO) DATA (including traffic, storm water management, reforestation, emergency management, & water usage)

July 2005 - Submitted Site Plan & APFO data to the town and county .for approval

 

√  HIRED GENERAL CONSTRUCTION CONTRACTOR for construction services and to support ongoing design effort

June 2005 - Selected Bruchey Builders (Frederick, MD) as the general contractor

Fall 2005 - Winter 2006

 SITE PLAN, APFO (Adequate Public Facilities Ordinance) and PUBLIC WORKS AGREEMENT APPROVED - Town and County approved Site Plan &  APFO

March 2006.  APFO approved April 2006

 

√  DESIGN & CONSTRUCTION DRAWINGS COMPLETED

Architect completed the design and construction drawings and documents

April 2006

Spring - Summer 2006

 
√  COST ESTIMATE (BASED ON BIDS) PREPARED BY CONSTRUCTION CONTRACTOR

May 2006

 

√  SIGN CONTRACT WITH CONSTRUCTION CONTRACTOR

May 2006

 

√  SECURE CONSTRUCTION LOAN

May 2006

 

√  SUBMIT GRADING & BUILDING PERMIT APPLICATIONS

May 2006

 

√  HOLD GROUND BREAKING CEREMONY

May 2006

 

√  RECEIVE GRADING PERMIT & START BUILDING CONSTRUCTION

June 2006

To view current status, and future plans, click here

Copyright 2005-2008 St. James' Episcopal Church. All rights reserved.

Webmaster, Frei Solutions, LLC. 

Last Updated: May 29, 2008